National Electrical Installation Standards

Standards as High as Your Own

 
?
Tuesday, August 29, 2017

Question:

Re: CQD answer published Tuesday, August 22, 2017 -Services and Generators

Good Morning, in regards to Monday’s 8-21-17 Code Question, I see now I did not word the question correctly.

The Utility Transformer feeds the Service Main Distribution Board (MDP). MDP then feeds normal power to a 4P ATS and the Generator feeds emergency power to the 4P ATS. The MDP gets a Main bonding Jumper and since the ATS is a 4 Pole, then the Generator (Separately Derived System) requires a System Bonding Jumper. Done.

But then It get confusing. The Utility Xfmr. also feeds the Fire Pump Controller (3 Pole ATS) for normal power. The generator supplies an emergency feed to the F.P Controller (3P-ATS), apparently they do not make 4 Pole Fire Pump Controller ATS’s since the F.P. motors are 3 Phase 480 volt and a neutral is not needed.

Question 1. Since 250.24(C) requires us to bring the grounded conductor (neutral) to all Service Disconnecting means. I now have a generator that feeds a 4 pole ATS via MDP and a 3 pole F.P/ Controller ATS. Since 1 ATS is 4 pole with switched neutrals and one is 3 pole with Norm. & Emergency neutrals bonded together. Wouldn’t that be a violation of 250.30(A)

Question 2. If I did not have to bring a neutral from the Utility Xfmr. & from the generator to the 3P Fire Pump Controller ATS that would solve my dilemma. Is there something in the code that would allow me to do that and not violate 250.24(C) ?

Thanks in advance for your help,

Kelly Wofford

A

Answer:

Hey Kelly thanks for the additional information.

As you indicate a grounded conductor is required to be connected to each service disconnecting means grounded conductor terminal or bus as stated in 250.24(C).  A main bonding jumper is installed in your MDP and also in the Fire Pump Controller because they are (and need to be) both service equipment. See 695.4(B)(3) for more about the fire pump disconnecting means.

Q1. The generator grounded conductor connection to the MDP is switched by the 4 pole ATS so the generator is a separately derive system as defined in Article 100.  The 3 pole Fire Pump ATS is OK because there is no grounded conductor (neutral) from the generator to that ATS installed and connected to the service grounded conductor .If you did it would violate 250.24(A)(5).  

Q2. You do need a grounded conductor from the utility transformer to the 3 pole Fire Pump ATS as mentioned in the answer to Q1 and as stated in 250.24(C). Notice that for separately derived systems 250.30(A)(3) uses the word "if" and does not require a grounded conductor to be installed. An affective fault current path must be provided either by an equipment grounding conductor or more likely a supply side bonding jumper depending on the overcurrent device location for the generator conductors.

If this doesn't help enough please send in an additional question.

ABOUT CQD: The Code Question of the Day (CQD) is NECA and ELECTRICAL CONTRACTOR Magazine’s flagship National Electrical Code (NEC®) public forum for the industry, sponsored by EATON. The daily distribution of Q&A generates a lively dialogue and shares relative Code-based practical responses.

SUBMIT YOUR CODE QUESTION: Click here to submit a question to for inclusion in an upcoming edition of the Code Question of the Day, or email codequestion@necanet.org

CHARLIE TROUT: Charles M. Trout, better known as Charlie, was a nationally known NEC® expert and author. He served on several NEC® technical committees and is past chairman of CMP-12. In 2006 Charlie was awarded the prestigious Coggeshall Award for outstanding contributions to the electrical contracting industry, codes and standards development, and technical training. Even though Charlie passed away in October of 2015, his work continues in spirit. NECA continues to maintain this question forum for its many subscribers in memory and recognition of all his significant contributions to making the NEC what it is today.

NECA STANDARDS: NECA publishes the National Electrical Installation Standards™ (NEIS™), a series of ANSI-approved performance and quality standards for electrical construction. NEIS can be purchased in the NECA Store in three formats: a printed or  PDF download of a standard or, as an  annual subscription service.

NECA SAFETY PRODUCTS & PUBLICATIONS: NECA produces electrical safety publications and products for the industry including jobsite safety guides, handbooks and resource kits. View a full listing of available resources and products »

IMPORTANT NOTICE: Unless the question requests a response based on a specific edition, all answers are based on the latest edition of NFPA 70® National Electrical Code®.

This correspondence is not a formal interpretation of the NEC® and any responses expressed to the questions are opinions and do not necessarily represent the official position of NECA, NFPA, the NEC Correlating Committee any Code-making panel or other electrical technical committee. In addition, this correspondence is neither intended, nor should it be relied upon, to provide professional consultation or services. 

UPDATE YOUR SUBSCRIPTION PREFERENCES: Subscribe or Unsubscribe from this list.